Beautiful Sunset

I stopped on Wed., because Steve had told me the peak of the roof was on. Darn snow slowed down the progress. I called Dan on Thurs. night to see how everything was going. He is going to Mexico w/ LS lumber on Sat., so he won't be working next week. The roofing guys are going to get started. Cool - until I checked out the weather for next week. By Wed. I think it is supposed to be 10 degrees again. My homework for this week is to go to KBL to look at fireplaces and go to Connor Plumbing to decide on bathroom stuff for the plumber.


Friday - I left work at 3:30, picked Jackie up at home and dropped her at school for the dance at 4. Drove to the ATM, UPS store to ship a broken toy back, and to the gas station. Picked up Josie at latchkey, and we went to the house. On the way, we saw this beautiful sunset and stopped to get a picture. Walked around the house, and then went to Schnucks for groceries. After that we went to Blockbuster for movies and picked Jackie up at school at 6pm, then on to home. I'm exhausted.


The left side of the house (as seen from the road) is the only open spot left on the roof. Dan said something about the roofing guys maybe papering the roof this weekend.



All of the roof is finally covered. It 's funny our back porch seems small now. Our house towers over the rest of our neighbors. Steve wants to know how tall the peak is. I should have him climb up there and find out.
Dan said they have been doing some things inside the house. Braces, hurricane clips, etc....


There were a couple things laying inside the house. Here is the garage door frame, and the soffit accessories.

I'll try to take some pics of our decision making of bathroom stuff. I think it will take much longer than we think.